From Cabinet
Construction of the Segment One of the Vaisigano River Protection Wall
Cabinet has approved the awarding of contract to Ott Constructors Ltd. for the construction of the Segment One of the Vaisigano River Protection Wall.
The tender for the project was advertised for public interest and eight companies responded.
An assessment was conducted by the Sub Committee according to the tender criterion.
After assessment a recommendation was submitted to Cabinet for the final decision.
Supply of Passports and Maintenance of the Border Management System
Cabinet has approved a two year contract to the Tardis Technology Pty Ltd. for the supply of Passports and three passport printers for the Samoa Immigration Office.
Cabinet has also approved the awarding of a two-year contract to Merit Technology Pty Ltd. for the Maintenance of the Boarder Management System.
Both contracts for these services will be tendered out after the current contracts.
Road reconstructions in Upolu and Savaii
Cabinet has approved the awarding of contacts to the following companies for the reconstruction of roads in Upolu and Savaii.
Upolu
Contract Name | Successful Contractor |
Re-Construction of Motootua Road | King Construction Ltd |
Construction of Link Road, Vaea St-TofafuafuaRd | Lucky Construction Ltd |
Re-Construction of Faipule Road, Faatoia | Ott Constructors Ltd |
Savaii
Contract Name | Successful Contractor |
Construction of Falesalafai Road, Salelologa | Big Island Construction |
The tender for the works were advertised for public interest. Six companies submitted applications of bids for Upolu works and four bids for Savaii works.
An assessment was conducted by the Tender's Committee according to the tender bidding document, before a recommendation was tabled before Cabinet for the final decision.
Variation works for Solid Waste Collection
Cabinet has approved the awarding of variation works to the following companies for Solid Waste Collection for Upolu and Savaii.
Zone | Successful Bidder | Duration |
A | Jaffas Sanitary System | January 2011 - June 2017 |
C1 | Bluebird Construction Ltd | January 2011 - June 2017 |
C2 | Bluebird Construction Ltd | January 2011 - June 2017 |
D1 | Bluebird Construction Ltd | January 2011 - June 2017 |
D2 | Iakopo Development | January 2011 - June 2017 |
E1 | Bluebird Construction Ltd | January 2011 - June 2017 |
E2 | Bluebird Construction Ltd | January 2011 - June 2017 |
F1 | Jaffas Sanitary System | January 2011 - June 2017 |
F2 | Jaffas Sanitary System | January 2011 - June 2017 |
Savaii West | Apia Lua Ltd. | January 2011 - June 2017 |
Cabinet has also approved the contract of variation works to Bluebird Construction Ltd. for the Tafaigata Landfill Maintenance.
Both contracts will be tendered out for duration of three years.